Block M Site Construction Progress

Markisa / Meritus Site Construction

 

Construction completed. Work included wellsite extension of approx. 2000 m² of open area for base camp & site office; relocation of septic tanks, new chemical storage & silt trap; and widening of entrance road. All unsuitable materials (soft soil & timbers) were disposed of at the north side of the wellsite area.

 

 Well site extension

 

New chemical storage

 

Thickness of pavement for wellsite extension is 300 mm of gravel with Tensar Triax – TX 160 Geogrid placed in the middle of the gravel for reinforcement.

 

Widening entrance to well site

 

Alternative Mahawu South Wellsite

 

Drilling boreholes completed at "Alt. 1" location on 13th February and at"Alt.2" on 7th March.
Geotechnical laboratory testing is in progress.

 

Alt 1, Mahawu

 

Alt 2, Mahawu

 

Earthworks at Access Road to Melati


Clearing, drainage ditch excavation at access road to Melati in progress and requires upgrade (fill and reinforcement) and widening of logging road.

 

 

 

 

Updated:2012-03-30

 

 