Markisa / Meritus Site Construction
Construction completed. Work included wellsite extension of approx. 2000 m² of open area for base camp & site office; relocation of septic tanks, new chemical storage & silt trap; and widening of entrance road. All unsuitable materials (soft soil & timbers) were disposed of at the north side of the wellsite area.
|
|
Well site extension
|
New chemical storage
|
Thickness of pavement for wellsite extension is 300 mm of gravel with Tensar Triax – TX 160 Geogrid placed in the middle of the gravel for reinforcement.
Widening entrance to well site
|
|
Alternative Mahawu South Wellsite
Drilling boreholes completed at "Alt. 1" location on 13th February and at"Alt.2" on 7th March.
|
|
Alt 1, Mahawu
|
Alt 2, Mahawu
|
Earthworks at Access Road to Melati Clearing, drainage ditch excavation at access road to Melati in progress and requires upgrade (fill and reinforcement) and widening of logging road.
|
|
|